We have moved forward on the Art Department’s relocation to
the Boh property in Gert Town, which will provide the Art Department
with 26,500 sq. ft. of building space for current needs and future
growth. We have completed the interior renovations to Building A, and
the sculpture and ceramics classes are presently occupying this space.
We are moving forward with Phase Two of this project, which should be
completed by the end of December 2002. Phase Two includes the renovation
of Building C to accommodate art education, computer graphics, a lecture
room and faculty offices. Phase Three, the renovations of Building D,
will include accommodations for drawing/painting, photography, printmaking
and faculty offices. If we can obtain access to this facility, and obtain
additional funding, we can have this facility ready for the fall semester
2002. Because of the known expenses associated with renovating the other
buildings on the square and some unknown factors, we are giving strong
consideration to demolishing buildings B and E instead of renovating
them. So far, the Title III grant has been the sole source of funding
to this project. The Art Department and Institutional Advancement both
feel that they can raise additional funds so that we can continue from
phase to phase without interruptions.
|